Thursday, 25 August 2016

INF 337 Week 3 Quiz

06:39

Share it Please
INF 337 Week 3 Quiz
1. The three key components of Earned Value are PV, AC and EV.
2. The following is the cost of all progress achieved on the project, or part of the project, and represents what has been spent.
3. Earned value describes what has been earned, not simply what has been spent.
4. A project variance can either be a positive or a negative number.
5. Accurate and up to date information on percentage of work packages completed is not important for EV.
6. Any significant deviations between actual and planned budget expenditures constitute what?
7. A formal financial review process is always necessary, even when a PM uses project cost control because of the many uncertainties with cost control.
8. AC is the actual cost of the work performed.
9. The 50/50 rule is used for packages with a very long duration.

10. Which of the following is a quantitative measurement?

0 comments:

Post a Comment